Snowfall Recovery: Power Supply Restored in Record Time

Chief Minister reports rapid restoration of power, with 37 out of 41 33KV feeders and 639 out of 739 11KV feeders fully operational post-snowfall disruption.

image

Snowfall Recovery: Power Supply Restored in Record Time

In a remarkable turnaround following the recent heavy snowfall, the state government has successfully restored power to a majority of affected areas. Chief Minister [Name] announced that 37 out of 41 33KV feeders and 639 of 739 11KV feeders have been recharged, significantly improving the power situation in the state.

The snowfall had wreaked havoc on the power infrastructure, leaving several areas without electricity for hours, if not days. However, the swift action taken by the government and the local power departments has proven effective in restoring normalcy. The efforts of field workers and engineers have been commendable, considering the challenges posed by the snow-covered terrain and technical difficulties.

Despite these efforts, some areas are still facing power interruptions. The Chief Minister emphasized that work is ongoing to restore the remaining feeders. "We are doing everything possible to ensure that the remaining areas are also connected to the grid soon," the CM assured.

While the restoration efforts have been largely successful, there are questions regarding the preparedness of the power infrastructure to handle such severe weather events in the future. Experts argue that more long-term solutions are needed to prevent such widespread disruptions in the future.

The government’s prompt response to the crisis has been appreciated, but it also highlights the need for better resilience in the power sector to avoid similar challenges in the future.